Tuesday November 17th 2026

Galafoot Bridge
Written by Local Democracy Reporter, Paul Kelly
A transport boss has delivered an “unwanted message” after announcing that users of a key Scottish Borders crossing face prolonged disruption.
It has been announced that major work to refurbish the deck of Galafoot Bridge on the A6091 is likely to continue until late January next year after the concrete deck underneath the road surface was found to be in significantly worse condition than expected.
Eastbound traffic on the bridge, that crosses the River Tweed in Galashiels, will be closed until late January 2027 after contractors Bear Scotland found the bridge’s concrete deck to be in a worse condition than anticipated.
The bridge has been restricted to westbound traffic only since October 5 while work is carried out on the eastbound side.
Surfacing and waterproofing have been removed and concrete repairs are currently under way but Bear Scotland said three times as much concrete requiring repairs has been found than originally anticipated
The refurbishment, managed by Bear Scotland on behalf of Transport Scotland, also includes resurfacing the carriageway and footpaths, renewing waterproofing, improving parapets and carrying out maintenance beneath the bridge.
Bear Scotland south east bridges manager David Bishop said: “The concrete deck slab under the road surfacing on Galafoot Bridge has been found to be in much worse condition than estimated.
“There was always some uncertainty over what we would find once we removed the existing road surface, however there is more than three times as much concrete requiring repairs as originally anticipated.
“This additional concrete repair area will increase the duration of the works. We’ve been working with our contractors to identify ways of accelerating the works, including bringing in additional resources, however there are still significant unknowns including the condition of the concrete under the westbound carriageway and the impact of weather over the weeks ahead.”
Full overnight closures are planned for November 2, from November 12 to 18, and on November 27.
Mr Bishop continued: “Assuming the deck under the other half of the bridge is in similar condition, and we experience weather that would typically be expected during November and December, it is likely that works will need to continue until the end of January 2027.
“We appreciate that this is an unwelcome message for local people and motorists who use the route, however it is essential that these repairs are completed thoroughly in order to preserve the structural integrity of the bridge and minimise the need for repeated future bridge closures.”