Plans for what would have been one of the biggest wind farms in the Borders which were dropped just a few weeks before a public inquiry was set to start are back on the agenda – but now on a much-reduced scale.
Muirhall Energy had wanted to erect 52 turbines – up to 240m (790ft) high – on hills at Priesthaugh, south of Hawick.
Scottish Borders Council (SBC) objected to the Teviot Wind Farm scheme and this summer the Scottish government’s planning and environmental appeals division began preparations for the inquiry.
Due to continuing uncertainty surrounding the policy framework for the Eskdalemuir Seismic Array, Muirhall Energy made the “difficult decision” in July to withdraw the initial application to bring forward a revised proposal.
Campaigners voiced their relief that the plans were withdrawn, but the company said at the time it intended to return with new proposals.
Now a scoping report on the revised plans has been prepared, to accompany a request for a Scoping Opinion to the Energy Consents Unit, on behalf of the Scottish Ministers.
The revised application is for the erection of 23 wind turbines with a maximum blade tip height of 240m and a generating capacity of approximately 188MW, plus a Battery Energy Storage System (BESS) facility with an installed capacity of 100MW.
A report with the application states: “The proposed development currently remains at an early stage of design and will continually evolve in response to the environmental survey work undertaken by the technical specialists, engineering requirements onsite, operational needs of the proposed development and consultation feedback from consultees and the public consultation events.”
Public consultation events are planned for Tuesday, December 8 (4pm to 8pm) and Wednesday, December 9 (10.30am to 2.30pm) at Muirhall Energy’s Office, 4-6 North Bridge Street in Hawick.
The project team will also be available for one-to-one meetings from 1pm-3pm ahead of the event on Tuesday, December 8. If you are interested in booking a slot with the team on this date please contact Teviot@muirhallenergy.co.uk.